Project Date : 2019 September
Project Location : Ratmate, Nuwakot
Client : Millennium Challenge Account : Nepal
Consultants : Stantec Nepal , Environment Resource Management(ERM), Total Management Services (TMS) Nepal Pvt. Ltd. and ADMC Engineering Pvt. Ltd.
Project Description : Substation at Ratmate, Nuwakot for 400KV Transmission Line
My work : Measurement of Structures (precision of millimeters) , Preparation of Building Plans and Valuation of Structures Affected by Substation Constructed at Ratmate Nuwakot for Preparation of Resettlement Action Plan (RAP) report.