Substation for 400KV Transmission Line at Nuwakot, Nepal

Description photo

Project Date : 2019 September

Project Location : Ratmate, Nuwakot

Client : Millennium Challenge Account : Nepal

Consultants : Stantec Nepal , Environment Resource Management(ERM), Total Management Services (TMS) Nepal Pvt. Ltd. and ADMC Engineering Pvt. Ltd. 

Project Description : Substation at Ratmate, Nuwakot for 400KV Transmission Line

My work : Measurement of Structures (precision of millimeters) , Preparation of Building Plans  and Valuation of Structures Affected by Substation Constructed at Ratmate Nuwakot for Preparation of Resettlement Action Plan (RAP) report.